Manhole Work Ongoing in Prescott Valley
2/6/23
If you’re driving in Prescott V alley, you’ll notice less bumps in the roads. The town is working to adjust all of the manholes in the community to pavement level with the project now at about 50 percent completion. Ninety manholes and 38 water valve cans, which are the smaller manhole covers, have been targeted for the project.
Construction has been completed on Stoneridge Drive, Viewpoint Drive and in the Quailwood Meadows subdivision. Crews finished work on Florentine Road on Thursday. Work continues this week on Robert Road from Florentine to Loos Drive. Residents can expect lane closures with slight delays possible.